How to use this calculator
- Choose US customary or metric measurements.
- Enter the length, width, and thickness of each rectangular section.
- Add sections for separate slabs, then choose a waste allowance.
- Calculate and review volume and bag estimates.
How the calculation works
This is the general-purpose concrete tool: it handles any mix of rectangular sections in one pass. Each section is length times width times thickness in feet, the sections are added, and one waste percentage is applied to the total. Use it when the job is a pad plus a walkway, or when you are not sure yet which specialized page fits. Bag counts are shown for comparison, rounded up.
Formula
Volume = length × width × thickness Cubic yards = cubic feet ÷ 27 Adjusted volume = base volume × (1 + waste % ÷ 100)
Worked example
An 8 ft by 8 ft pad and a 3 ft by 20 ft walkway, both 4 in thick, are entered as two sections. The pad holds 21.33 cubic feet and the walkway 20 cubic feet, so the base volume is 41.33 cubic feet. With 10% waste the order is 45.47 cubic feet, or 1.68 cubic yards. In 80 lb bags at a nominal 0.6 cubic feet each, that is 75.8, so 76 bags.
Coverage at common thicknesses
The table is the formula applied to 100 square feet of surface. It is useful for a sanity check: if your result is far from these numbers for your area and thickness, recheck the inputs.
| Thickness | Cubic feet per 100 sq ft | Cubic yards per 100 sq ft | Cubic yards with 10% waste | Sq ft covered by 1 cubic yard |
|---|---|---|---|---|
| 4 in | 33.33 | 1.23 | 1.36 | 81.0 |
| 5 in | 41.67 | 1.54 | 1.70 | 64.8 |
| 6 in | 50.00 | 1.85 | 2.04 | 54.0 |
Bags or a truck?
Using the nominal yields from the bag calculator, one cubic yard is 90 bags of 40 lb mix, 60 bags of 60 lb mix, or 45 bags of 80 lb mix. In every case that is about 3,600 pounds of dry mix per cubic yard, which is why bagged concrete stops being practical for larger jobs. The 1.68 cubic yard example above would mean carrying and mixing roughly 6,080 pounds of bagged mix (76 bags at 80 lb).
Ready-mixed concrete is delivered by volume. Ask the supplier about minimum loads and any short-load charge before deciding, because the best choice depends on local pricing and how much you can place and finish before the concrete stiffens.
Unit mistakes that change the answer
- Treating 4 inches as 4 feet multiplies the result by twelve. Divide inches by 12 first, or use the inches field.
- Quoting cubic feet to a supplier who sells cubic yards. Divide by 27.
- Mixing metric and US values within one section.
- Rounding each section before adding them. Add first, round once at the end.
Project considerations
- Enter every section at its own thickness instead of averaging, so a thicker pad and a thinner walkway are not blended.
- Keep one unit system per calculation. The most common error is a thickness typed in inches into a field that expects feet, or the reverse.
- If the project is a driveway, a slab with thickened edges, or a bag-only job, the dedicated pages explain details specific to those cases.
Frequently asked questions
When should I use this page instead of the slab or driveway pages?
Use it when the project has mixed shapes or you only need a quick volume. The slab, driveway, and bag pages add context about edges, joints, and rounding that this page does not repeat.
How many bags make a cubic yard?
Using the nominal yields on the bag page, 90 bags of 40 lb, 60 bags of 60 lb, or 45 bags of 80 lb. Check the yield printed on the product you buy.
Why include a waste percentage at all?
Forms are rarely perfect and the ground is rarely flat. A shortfall in the middle of a pour is far more costly than a small surplus, so most people add a margin and choose it from site conditions.