Break the job into simple shapes, find each shape’s volume in cubic feet, add them, and divide by 27 for cubic yards. This guide covers what goes beyond a plain rectangle, such as post holes, wedges, and several pours, and how to decide between buying bags and ordering by the truckload.

Use the Concrete Calculator

Sort the job into shapes

Most projects are a handful of familiar solids. Calculate each one on its own and add the results.

Boxes
Pads, walkways, and footings are length times width times depth.
Cylinders
Post holes, piers, and round columns use π × radius² × height. Radius is half the diameter.
Wedges
A ramp that tapers from nothing to full thickness is half of the box that would enclose it.
Repeated parts
Calculate one hole or one footing, then multiply by the count.

Formulas for common shapes

Box = length × width × depth
Cylinder = π × (diameter ÷ 2)² × height
Wedge = ½ × length × maximum thickness × width
Cubic yards = cubic feet ÷ 27

Convert every dimension to feet before multiplying. Ten inches is 0.8333 ft, and a radius of 5 inches is 0.4167 ft.

Worked example: a pad, six post holes, and a ramp

A job has an 8 ft by 6 ft pad 4 inches thick, six round holes 10 inches in diameter and 36 inches deep, and a ramp 6 ft wide and 4 ft long that tapers to 6 inches thick. The allowance is 10%.

  1. Pad: 8 × 6 × 0.3333 = 16.00 ft³
  2. One hole: π × 0.4167² × 3 = 1.636 ft³; six holes = 9.82 ft³
  3. Ramp: ½ × 4 × 0.5 × 6 = 6.00 ft³
  4. Base total: 16.00 + 9.82 + 6.00 = 31.82 ft³
  5. With 10%: 31.82 × 1.10 = 35.00 ft³; ÷ 27 = 1.30 yd³

Result: The order is about 35 cubic feet, or 1.30 cubic yards. In 80 lb bags at a nominal 0.6 cubic feet each, that is 58.3 bags, so 59.

Bags or a truck

One cubic yard is 45 bags of 80 lb mix at a nominal 0.6 cubic feet per bag, about 3,600 pounds of dry material. The 1.30 cubic yard example means lifting and mixing roughly 4,700 pounds of bagged mix (59 bags at 80 lb). That is workable for a few small pours and is hard for one person in one afternoon.

Ready-mixed concrete is billed by volume and often has minimum loads or short-load charges. Ask your supplier what applies, because the break-even between bags and a truck depends on local prices and on how much you can place and finish before the concrete stiffens.

Mistakes specific to mixed shapes

Using diameter where radius belongs
Doubling the radius quadruples the cylinder volume. Entering 10 inches instead of 5 inches overstates each hole by a factor of four.
Counting overlaps twice
Where a pad sits on top of a footing, count each piece once. Calculate the footing to its top and the pad separately.
Forgetting the wedge fraction
A ramp is half of its enclosing box, not the whole box.
Applying waste to each part
Add the shapes first, then apply one allowance to the total.

Concrete quantity questions

Should separate pours be combined?

Combine them to compare with a delivery quantity, but keep each part visible so the dimensions are easy to check.

Which calculator handles round columns and stairs?

The concrete column and concrete stairs calculators. The general concrete calculator handles rectangular sections.