How to Calculate Concrete for a Slab
Measure slab length, width, and thickness, then convert the resulting volume to cubic yards with a clearly stated waste allowance.
Last reviewed: November 11, 2026
The short answer
A slab’s concrete quantity is set by the space between the top of the forms and the ground, so the number that matters is the average depth you actually measure, not only the thickness on the drawing. Measure the footprint, sample the depth at several points, find the average, and then convert.
Use the Concrete Slab CalculatorMeasure the ground before you measure the slab
Do this once the forms are set and the base is prepared, because it is the only moment the real depth is visible.
Set the form height
The top of the forms is the finished surface. Every depth is measured from that line.
Measure depth on a grid
Take readings every few feet in both directions, and extra readings near edges where ground tends to be lower.
Average the readings
Add the depths and divide by the number of readings. Use this average as the thickness.
Multiply by the footprint
Footprint area times average depth in feet gives cubic feet.
Convert and add the allowance
Divide by 27 for cubic yards, then apply the allowance once.
Average-depth formula
Average depth = sum of readings ÷ number of readings Cubic feet = footprint area × average depth (in) ÷ 12 Cubic yards = cubic feet ÷ 27
A slab that slopes evenly can be handled with two readings: the average of the high edge and the low edge.
Worked example: a 14-by-10-foot slab on uneven ground
The drawing says 4 inches. Six depth readings measured from the top of the forms are 3.5, 4, 4.5, 4, 4.5, and 5 inches. The planning allowance is 5%.
- Average depth: 25.5 ÷ 6 = 4.25 in
- Footprint: 14 × 10 = 140 ft²
- Volume: 140 × 4.25 ÷ 12 = 49.58 ft³
- With 5%: 49.58 × 1.05 = 52.06 ft³ = 1.93 yd³
Result: A flat 4 inch slab would be 46.67 cubic feet. The measured ground adds about 2.9 cubic feet, roughly 6%, before the allowance.
Edges and thickened perimeters
Some slab designs are deeper around the edge. Treat the thicker band as extra concrete under the perimeter. For the 14 ft by 10 ft slab, a 1 ft wide band has an area of 140 minus the inner 12 ft by 8 ft rectangle (96), which is 44 square feet. If the band is 8 inches deeper than the field, it adds 44 × 8 ÷ 12 = 29.33 cubic feet.
The depth and width of any thickened edge come from the plan or the person designing the slab. The slab calculator takes the band as four extra rectangles.
Checks before you order
- Slope
- If the top is pitched for drainage over a flat base, the high side is thicker. Average the two edges.
- Form dimensions
- Measure inside the forms, which is the space the concrete fills.
- Base material
- Gravel under the slab is a separate order. Use the gravel calculator for it.
- Units
- Label feet and inches on your notes, because an unlabeled thickness is a common source of large errors.
Slab questions
Does this method determine slab thickness?
No. Thickness, reinforcement, and base come from the project plan, site conditions, and local requirements.
What if the ground is much lower in one corner?
Add readings near that corner, or treat the low area as its own rectangle with its own average depth.