Concrete & Masonry

Concrete Slab Calculator

Estimate concrete for rectangular slabs with individual dimensions, a shared waste allowance, surface-area totals, and optional bag equivalents.

Last reviewed: November 11, 2026

Project measurements

Measurement system

Slab 1

How to use this calculator

  1. Choose US customary or metric measurements.
  2. Enter each slab’s finished length, width, and thickness.
  3. Add separate slabs when the project has more than one rectangular pad.
  4. Set a waste allowance and calculate the combined volume, area, and bag equivalents.

How the calculation works

A slab is calculated as a box, and this page adds up the volume and the top surface area of every slab you enter. The important slab-specific point is that real slabs are rarely one uniform thickness. Edges, steps in the subgrade, and drainage slope all change the average thickness, so the calculator lets you enter extra slabs to represent those thicker strips instead of hiding them in one number.

Formula

Slab volume = length × width × thickness
Combined volume = slab 1 + slab 2 + …
Adjusted volume = combined volume × (1 + waste % ÷ 100)

Worked example

A 12 ft by 10 ft slab is 4 in thick in the field and has a 1 ft wide perimeter strip that is 8 in deeper, as shown on the plan. The field is 40 cubic feet. The perimeter strip is two 12 ft by 1 ft pieces and two 8 ft by 1 ft pieces, 40 square feet in all, at 8 in: 26.67 cubic feet. Together that is 66.67 cubic feet. With 10% waste the order is 73.33 cubic feet, or 2.72 cubic yards, against 1.63 cubic yards for a plain 4 in slab. Enter the strips as four extra slabs; the reported top area will then be 40 square feet too high, so use the area from the main slab.

Edges, forms, and thickness changes

The form boards define the finished footprint and the top elevation. The volume is controlled by the distance between the top of the forms and the prepared ground, which is why measuring depth at several points on the subgrade is worth the time. A slab drawn as 4 inches that is actually 4.5 inches on average needs about 12.5% more concrete.

That last figure is just arithmetic: 4.5 divided by 4 is 1.125. On a 12 ft by 10 ft slab it is five extra cubic feet, or about 0.19 cubic yards, before waste.

How the details change the quantity

DetailEffect on volumeHow to enter it
Uniform slab on a flat baseLength x width x thicknessOne slab
Thickened perimeterExtra depth times the perimeter strip areaMain slab plus separate strips at the extra depth
Slab pitched for drainageAverage of thin and thick edge, times areaOne slab at the average thickness
Uneven subgradeAverage measured depth times areaOne slab at the average thickness

Project considerations

  • Measure the inside faces of the forms, because that is the space the concrete fills.
  • Dimensions of thickened edges, base layers, and reinforcement come from your plan or a qualified designer, not from this tool.
  • The surface-area total counts every slab you enter, so extra strips for edges will overstate it.
  • Bag equivalents use 0.30, 0.45, and 0.60 cubic feet for 40 lb, 60 lb, and 80 lb bags. Verify against the product label.

Frequently asked questions

How do I enter a slab with thickened edges?

Enter the main slab at its field thickness, then add the perimeter as separate non-overlapping strips at the extra depth. The worked example shows the arithmetic.

How do I handle a slab that slopes for drainage?

If the surface is pitched over a flat base, the thickness changes linearly across the slab, so the average of the thinnest and thickest points gives the right volume. A 10 ft wide slab that is 4 in at the low edge and drops 1/4 in per foot is 6.5 in at the high edge, an average of 5.25 in, about 31% more than 4 in.

Can I enter slabs with different thicknesses?

Yes. Each slab has its own thickness field.